Yard Gas Piping
10 Lb air test required at time of inspection (must hold for 15 minutes).
Factory coated pipe required under round and 6" above ground - all fittings and wrench marks to be primed and taped with 10 mil tape
Approved P.V.C. or polyethylene pipe is allowed - must be 18" below ground with 18 gauge tracer wire. Transition fitting to metallic pipe is required
Per chapter 12, Uniform Plumbing Code